Corrective Action

ID Action Number Description Priority Due At Status Completed At Verified At Isolation Event Audit Finding Owner Person
1 ISO-ACT-2026-00051 Introduce an end-of-shift lock reconciliation at t... HIGH 2026-08-15 00:00 IN_PROGRESS - - Contractor fitter departed site at end of shift wi... - E-3002
2 ISO-ACT-2026-00052 Amend TMPL-CV-101 to require the chute gate to be ... MEDIUM 2026-08-31 00:00 COMPLETE 2026-07-20 00:00 2026-07-21 00:00 Zero-energy verification failed at the chute gate ... - E-3003
3 ISO-ACT-2026-00048 Configure independent-verification enforcement so ... HIGH 2026-09-30 00:00 OPEN - - - Two isolation records showed zero-energy verificat... E-3003
4 ISO-ACT-2026-00049 Complete lock register inspection sweep and record... LOW 2026-09-30 00:00 OPEN - - - Six personal locks in the register have no recorde... E-3006
of 1